 CIP Division Responsibilities

 The CIP Division plans, develops, and implements the City’s Capital Improvement Program
 for streets, water mains, sidewalks, storm drains, drainage and traffic signals.
  
 Current CIP Division Projects

 Project No.

 Project Title

Phase

 ST1221

 McDowell Pedestrian Crossing

 Design

 ST1260

 Phoenix Children's Hospital

 Design

 ST1279/80

 Dysart Rd Pavement Preservation (ARRA Project)

 Design

 ST1020

 Preventative Street Maintenance 

 Construction

 ST1158

 Elm Lane Drainage Mitigation

 Construction

ST1162

CDBG Street and Sidewalk Improvements

Construction

ST1179

 Avondale Boulevard & Encanto Boulevard

Construction

 ST1260

 Avondale City Center 

 Construction

 ST1261

 Northwest Public Safety Facility 

 Construction

 

 

 
































Link to CIP Project Schedules



 *CIP Plan Approval Process

 

Step 1
Consultant
Given
NTP

 Step 2
15% Submittal Grade & Alignment (G&A)

Step 3
Over the Shoulder Review
15% G & A

Step 4
30%
Submittal

Step 5
City Review
30% Plans
(3 weeks)

Step 6
30% Comment Resolution Meeting

Step 7
Utility Coordination Meeting

Step 8
60% 
Submittal
 

Step 9
City Review
60% Plans (3-4 weeks)

Step 10
60% Comment Resolution Meeting

Step 11
90% Submittal

Step 12
City Review
90% Plans
(3-4 weeks)

Step 13
90% Comment Resolution Meeting

Step 14
Final
Submittal

 

 

 

 


*NOTE:  This is the Standard Process for CIP projects.  The City reserves the right to increase
or decrease the submittal requirements, number of submittals, number of review periods, or
number of meetings, as necessary, to accommodate each project.

Utility Coordination Requirements

Capital Improvement Projects (CIP) Standard Cover